Many AC EV wallbox manufacturers already have mature charging products with stable main controllers, established hardware designs, and tested safety systems. However, as the EV charging industry moves toward advanced communication features such as Plug & Charge (PnC), smart charging, and bidirectional power transfer, manufacturers increasingly need to upgrade their existing products to support ISO 15118-20.
Replacing an entire main control board can involve substantial hardware redesign, firmware redevelopment, and additional validation work. A more modular approach is to integrate an embedded Supply Equipment Communication Controller (SECC) module while retaining the existing AC EVSE main controller.
This approach can reduce the scope of hardware modifications, provided that the existing controller, PLC communication path, electrical interfaces, and firmware architecture are compatible with the new module.

Upgrading an AC EV wallbox to ISO 15118-20 enables more advanced communication between electric vehicles and charging equipment without necessarily changing the entire charging control architecture.
ISO 15118-20 is the second-generation vehicle-to-grid communication standard. It defines communication requirements between the Electric Vehicle Communication Controller (EVCC) and the Supply Equipment Communication Controller (SECC), including communication sequences for bidirectional power transfer.
For AC EV charger manufacturers, supporting ISO 15118-20 can provide several important advantages.
Plug & Charge Authentication
Plug & Charge allows compatible electric vehicles and charging stations to exchange identification and authorization information automatically. Drivers do not need to rely on traditional RFID cards or charging applications for every charging session.
Advanced Smart Charging
ISO 15118 communication enables the vehicle and charging equipment to exchange charging requirements and relevant energy information, supporting more intelligent charging coordination.
Bidirectional Power Transfer
ISO 15118-20 includes communication functions for bidirectional power transfer (BPT), creating opportunities for future V2G and V2H applications when the vehicle and charging system have compatible bidirectional power hardware.
Long-Term Product Compatibility
Adding an ISO 15118-20-capable communication architecture can help manufacturers prepare existing product platforms for evolving EV communication requirements and new charging applications.
Manufacturers should also check the exact standard edition required by their customers. The official ISO catalogue now lists Amendment 1:2026 to ISO 15118-20:2022, covering AC DER services, MCS services, and an improved security concept.
Reference: ISO 15118-20:2022 – Official International Standard
Yes, an existing AC EV wallbox can potentially support ISO 15118-20 through an additional SECC communication module if its main controller has compatible interfaces, sufficient processing resources, and an appropriate PLC communication architecture.
The key is to distinguish communication processing from overall charging control.
In a typical AC wallbox, the main controller is responsible for several functions:
Contactor and charging-state control.
Energy metering and charging management.
Safety monitoring and protection coordination.
User interface and authorization functions.
Network connectivity and OCPP communication.
An embedded SECC module can take responsibility for the high-level communication between the EV and EVSE, allowing the existing controller to retain its main charging management responsibilities.
However, not every existing wallbox can be upgraded through a simple module installation.
Before selecting this approach, manufacturers should evaluate three important conditions.
1. Main Controller Compatibility
The existing MCU should provide an available communication interface, such as UART, and sufficient resources to integrate the SECC module's communication and charging-state information into the existing firmware.
2. PLC Communication Hardware
ISO 15118 requires Power Line Communication (PLC) between the EV and EVSE. If the existing wallbox does not have a suitable PLC communication path, additional hardware integration will be necessary.
3. CP/PP Signal Compatibility
Control Pilot (CP) and Proximity Pilot (PP) related functions must be considered during integration. Depending on the selected module configuration, signal detection, PWM generation, and other functions may need to be implemented or retained on the existing AC main control board.
Therefore, the objective is not simply to add a new communication board. It is to establish a compatible communication interface between the existing controller and the new SECC module.
An embedded SECC module works as a dedicated communication component between the electric vehicle and the existing AC EVSE main controller, allowing the original controller to retain its charging management functions.
A typical retrofit architecture can be represented as follows:
Electric Vehicle (EVCC) | CP / PLC Communication | Charging Connector | PLC Coupling Circuit | Embedded SECC Module (ISO 15118-20 Stack) | UART | Existing AC EVSE Main MCU | +---------+---------+ | | | Contactor Metering Protection | | | +---------+---------+ | HMI / Network / OCPP
In this architecture, the SECC module handles EV-to-EVSE high-level communication, while the existing main controller continues managing the charging equipment.
For example, the main controller can receive communication status and charging-related information from the SECC module and use this information within its existing charging control logic.
This modular architecture offers several practical advantages:
Existing contactor control and metering designs can potentially be retained.
Existing user interfaces and backend connections do not necessarily need to be redesigned.
Communication functionality can be upgraded independently of the main control hardware.
Manufacturers can evaluate new communication features before committing to a complete controller redesign.
However, the physical PLC coupling path, CP signal routing, electrical isolation, and communication interface must all be verified against the actual wallbox schematic.
A successful ISO 15118-20 retrofit requires a structured hardware and software integration process, starting with controller assessment and ending with system-level interoperability testing.
Start by documenting the current charging system.
Important information includes the main MCU model, PCB schematic, available UART interfaces, charging connector type, CP/PP circuit design, power supply, and existing firmware architecture.
Manufacturers should also identify which functions are already handled by the main controller and which communication functions need to be added.
This assessment determines whether the existing platform can accommodate an embedded SECC module without replacing the main controller.
Not every manufacturer needs to implement every ISO 15118-20 function in the first upgrade.
For example, a residential AC wallbox may initially prioritize External Identification Means (EIM) and Plug & Charge, while a manufacturer developing future bidirectional charging products may also require BPT communication support.
The target functionality should be established before selecting the module and planning firmware integration.
The new SECC module must fit the existing PCB layout and operate within the wallbox's electrical environment.
Consider the following technical parameters:
| Parameter | Example integration requirement |
|---|---|
| Communication interface | UART or another supported host interface |
| Power supply | Stable voltage and sufficient current capacity |
| PCB dimensions | Available installation space |
| Connector | Compatible pin count and pitch |
| CP/PP circuits | Compatible signal routing and detection |
| Thermal conditions | Suitable operating temperature |
| PLC circuit | Compatible communication coupling path |
For example, the AUPINS AP-SE-B module uses a compact 50 × 10 × 30 mm board design with a 2.0 mm pitch, 18-pin single-row header.
Its published power requirement is 5V DC ±0.2V with a supply capacity greater than 600mA. Manufacturers should verify that the existing power supply can meet this requirement without affecting other control-board components.
Once hardware compatibility is confirmed, the next step is host-controller firmware integration.
The engineering team should establish the communication protocol between the SECC module and the existing MCU, including message formats, charging states, status reporting, error handling, and timeout recovery.
The main controller must correctly interpret communication events and coordinate them with existing charging-control functions.
Firmware integration should also account for version management, watchdog behavior, diagnostic information, and safe recovery from interrupted communication.
ISO 15118 communication support and a complete Plug & Charge deployment are not the same thing.
Plug & Charge projects require additional infrastructure, including certificate provisioning, Public Key Infrastructure (PKI), secure key storage, EVSE identity management, and compatible backend processes.
The CharIN Plug & Charge Implementation Guide provides useful guidance on the certificate and implementation requirements.
Manufacturers should also distinguish ISO 15118 communication from OCPP backend communication.
ISO 15118 manages communication between the vehicle and charging equipment, whereas OCPP provides communication between the charging station and its central management system.
According to the Open Charge Alliance, OCPP 2.0.1 supports ISO 15118 Plug & Charge, while OCPP 2.1 adds support for ISO 15118-20 bidirectional power transfer and Distributed Energy Resource (DER) control.
For this reason, an SECC upgrade should include a separate assessment of the existing OCPP and backend architecture, particularly when BPT or energy-management functions are required.
The final stage is to verify that the upgraded wallbox operates reliably as a complete system.
Testing should cover PLC communication establishment, EVCC-SECC message exchange, EIM authorization, Plug & Charge certificate workflows, and BPT communication where applicable.
Engineers should also test CP/PP signal handling, charging-state transitions, communication interruptions, timeout recovery, firmware updates, and regression of existing charging functions.
Interoperability testing with representative EVs or EVCC test equipment is particularly important. A module's protocol support alone does not establish that the complete wallbox is compliant or interoperable.
The best upgrade strategy depends on the existing controller's hardware capabilities, available communication interfaces, required charging functions, and expected development effort.
The following table compares three common approaches for AC EV charger manufacturers.
| Evaluation | Add an Embedded SECC Module | Replace Main Controller | Redesign the Charging System |
|---|---|---|---|
| Existing MCU | Retained if compatible | Replaced | Replaced or substantially redesigned |
| Hardware changes | Additional module and necessary interface modifications | New controller and related connections | Broad hardware changes |
| Firmware work | Host-to-SECC integration | New controller firmware integration | Full system redevelopment |
| Existing safety functions | Can potentially be retained | Requires system revalidation | Requires comprehensive revalidation |
| Development scope | Relatively limited when compatible | Moderate to extensive | Extensive |
| Best application | Existing controller has suitable interfaces | Existing MCU lacks required capabilities | Major architecture or power-system changes |
For manufacturers with a mature AC wallbox platform, adding an embedded SECC module is often worth evaluating first.
It can preserve existing hardware investments while introducing new communication capabilities. However, if the original MCU lacks sufficient resources, the PCB has no practical space for integration, or the existing PLC and CP architecture cannot support the target functions, replacing the main controller may be the more reliable option.
AUPINS AP-SE-B is an embedded AC SECC PLC communication module designed to help EV charger manufacturers integrate ISO 15118 communication into existing AC charging equipment.
The AP-SE-B combines PLC communication hardware with ISO 15118 protocol support, providing a modular option for manufacturers who already have an AC EVSE main controller.
Its published technical specifications include:
| Technical Parameter | AP-SE-B Specification |
|---|---|
| Module dimensions | 50 × 10 × 30 mm |
| Pin header | 18-pin, single-row |
| Pin pitch | 2.0 mm |
| Communication interfaces | UART × 2, USB × 1 |
| Power supply | 5V DC ±0.2V, greater than 600mA |
| Operating temperature | -40°C to +85°C |
| Charging interfaces | CCS1, CCS2, NACS |
| Protocol support | ISO 15118-2 and ISO 15118-20 |
| Communication functions | EIM, PnC, BPT/V2X |
| Additional functions | OTA upgrade, log storage and retrieval |
The module also supports optional CP detection, PD/PP detection, PWM generation, and E-state control functions. Depending on the selected configuration, the related circuits may need to be implemented on the AC main control board.
One important advantage is its host-controller integration capability. The two UART interfaces allow AP-SE-B to communicate with the MCU on the existing AC EVSE main control board.
This makes it particularly relevant for manufacturers who want to preserve their existing charging-control architecture while introducing ISO 15118 communication.
It is important to understand that AP-SE-B is an embedded communication module, not a complete AC charger controller. Contactor management, energy metering, protection, user interface, and backend connectivity remain part of the overall EVSE system.
For OEMs evaluating different controller architectures, explore the AUPINS EV Charger Control Board product range.
You can also review the AP-SE-B ISO 15118-20 AC SECC PLC Communication Module for its detailed specifications and application information.
Before moving to mass production, manufacturers should confirm the pin definition, mechanical drawing, communication protocol, firmware version, and optional circuit requirements with the engineering team.
Upgrading an existing AC EV wallbox to ISO 15118-20 does not always require replacing the entire main controller. By integrating an appropriate embedded SECC communication module, manufacturers may be able to retain their existing charging-control architecture while adding advanced EV-to-EVSE communication capabilities.
However, successful integration depends on more than protocol compatibility. Main MCU resources, UART interfaces, PLC coupling, CP/PP signal routing, power supply, firmware coordination, certificate management, and system-level validation must all be considered.
For EV charger OEMs looking for a modular upgrade solution, AUPINS AP-SE-B offers an embedded PLC and SECC communication platform with ISO 15118-2 and ISO 15118-20 support.
If you are planning to upgrade an existing AC wallbox, contact the AUPINS engineering and sales team with your current controller specifications and target communication requirements to discuss module compatibility, technical documentation, and sample evaluation.
Not necessarily. ISO 15118-20 requires compatible PLC communication hardware, an SECC implementation, appropriate signal interfaces, and firmware integration. Some existing chargers will require additional hardware.
No. An SECC module handles high-level communication between the EV and EVSE. The main controller normally continues managing contactors, metering, protection, user interfaces, and other charging functions.
UART is a common host-controller communication interface. For example, AP-SE-B provides two UART interfaces and one USB interface. The actual integration requirements depend on the MCU, electrical specifications, and firmware architecture.
Yes, if the SECC module, EVCC, certificate infrastructure, secure key storage, and backend systems support the required Plug & Charge functions. Installing a compatible communication module alone does not complete the entire deployment.
No. ISO 15118-20 provides communication functions for bidirectional power transfer, but a complete V2G or V2H system also requires compatible vehicles, bidirectional power electronics, energy management, and applicable grid protection and compliance.
Manufacturers should provide the main-controller model, PCB schematic, available UART interfaces, power supply specifications, charging connector type, CP/PP circuit design, and required ISO 15118 functions. AUPINS can use these details to assess the integration requirements before sample evaluation.